TRANSITION PIECE INSTALLATION (#101)
OFFSHORE WIND MARINER UPDATE NO. 101
STATUS: Active
Beginning in May, the jack-up vessel SEA CHALLENGER will be installing transition pieces at 17 monopile locations in Lease Area OCS-A 0501.
Standing by on VHF channel 16
DATE(S): Beginning in May and continuing through June 2024
LOCATION(S): OCS-A 0501 Lease Area
SEA CHALLENGER
Flag: Denmark
Length: 434’
MMSI: 219019002