PRE-LAY SURVEY OPERATIONS FOR MID-SECTION CABLE LAYING OPERATIONS (#74)

OFFSHORE WIND MARINER UPDATE NO. 74

STATUS: Active

The 45’ R/V HENRY HUDSON and 32’ R/V JIM COLE will be performing survey operations in the offshore cable corridor in the vicinity of Muskeget Channel in preparation for Cable Laying Operation.  Vessels will be standing by on VHF channel 16.

 
DATE(S): On or about the 2nd of February for a period of two-three weeks, weather permitting.

LOCATION(S): Offshore Export Cable Corridor in the vicinity of Muskeget Channel

Standing by on VHF channel 16

R/V HENRY HUDSON

Flag: USA
Length: 45'
MMSI: 367541190

R/V JIM COLE

Flag: USA
Length: 32'
MMSI: 338242135

For the latest information, please contact:
VINEYARD WIND

Crista Bank, Fisheries Manager, Cell: 508-525-0421 • Email: cbank@vineyardwind.com

Jeannot Smith, Marine Liaison, Cell: 904-613-0134 • Email: jsmith@vineyardwind.com

Travis Lowery, Fisheries Liaison, Cell: 08-728-4529 • Email: tlowery@vineyardwind.com

 
 

VineyardWind.com • info@vineyardwind.com • 508-717-8964
700 Pleasant Street, Suite 510 • New Bedford, MA 02740