INTER-ARRAY CABLE ROUTE PRE-LAY MULTIBEAM SURVEY (#86)

OFFSHORE WIND MARINER UPDATE NO. 86

STATUS: Active

Beginning on or about July 6th, 2023, the GASPEE will be performing a pre-lay multibeam survey operation along the inter-array cable route in OCS-A 501 lease area. The survey operations, weather permitting, will take approximately 4-5 days. The vessel will not be towing any gear for this operation. 

Standing by on VHF channel 16

 
DATE(S): Beginning on or around July 6th and continuing for about 4-5 days

LOCATION(S): In the vicinity of inter-array cables in OCS-A 501 lease area (See attached chart)

GASPEE

Flag: USA
Length: 135’
MMSI#: 367584050

 

For the latest information, please contact:
VINEYARD WIND

Crista Bank, Fisheries Manager, Cell: 508-525-0421 • Email: cbank@vineyardwind.com

Jeannot Smith, Marine Liaison, Cell: 904-613-0134 • Email: jsmith@vineyardwind.com

Travis Lowery, Fisheries Liaison, Cell: 508-728-4529 • Email: tlowery@vineyardwind.com

 
 

VineyardWind.com • info@vineyardwind.com • 508-717-8964
700 Pleasant Street, Suite 510 • New Bedford, MA 02740

archiveMoreschi