TOWER AND WIND TURBINE GENERATOR (WTG) INSTALLATION (#93)

OFFSHORE WIND MARINER UPDATE NO. 93

REVISED

STATUS: Active

Beginning in September the jack-up vessel SEA INSTALLER will be installing the Towers and Wind Turbine Generators (WTG's) in OCS-A 501. The installation will begin at positions that have Monopile Foundations (MPs) and Transition Pieces (TPs) installed. This work will also include blade work and maintenance.

The feeder barges MARMAC 400 & PREVAILING WINDS, assisted by the tugs NICOLE FOSS, MICHELE FOSS, EARL W REDD, HAWAII FOSS, will assist in supplying materials for installation from the staging area in New Bedford, MA. The OSV CADE CANDIES and C-PIONEER will be supporting crew transfer operations.

Standing by on VHF channel 16

DATE(S): Beginning in September 2023 and continuing in 2025

LOCATION(S): Completed monopile foundation (MP) and transition piece (TP) locations in OCS-A 501 lease area

 

SEA INSTALLER

Flag: Denmark
Length: 434’
MMSI#: 219456000

NICOLE FOSS

Flag: USA
Length: 130’
MMSI#: 367774490

MICHELE FOSS

Flag : USA
Length: 
130’
MMSI#:
367657270

EARL W REDD

Flag: USA                 
Length: 
89’
MMSI#:
367765170

HAWAII FOSS

Flag: USA
Length: 105’
MMSI#: 368296000

CADE CANDIES

Flag: USA
Length: 200’
MMSI#: 369108000

C-PIONEER

Flag: USA
Length: 260’
MMSI:  368291370


For the latest information, please contact:
VINEYARD WIND

Crista Bank, Fisheries Manager, Cell: 508-525-0421 • Email: cbank@vineyardwind.com

Jeannot Smith, Marine Liaison, Cell: 904-613-0134 • Email: jsmith@vineyardwind.com

Travis Lowery, Fisheries Liaison, Cell: 508-728-4529 • Email: tlowery@vineyardwind.com

 
 

VineyardWind.com • info@vineyardwind.com • 508-717-8964
700 Pleasant Street, Suite 510 • New Bedford, MA 02740

activeMoreschi