INTER-ARRAY CABLES INSTALLATION (#95)
OFFSHORE WIND MARINER UPDATE NO. 95
REVISED
STATUS: Active
Beginning on or around September 10th and continuing through November 2023, cable laying operations for the inter-array cables will be conducted, beginning with array cable lines 5 and 6.
The Cable Laying Vessel ISAAC NEWTON will be conducting cable laying operations for the inter-array cables and will remain on-site until early October.
The C-PIONEER will be acting as a stationary support vessel, supporting cable pulling activities for the inter-array cables.
The Trenching Support Vessel ADHEMAR DE SAINT-VENANT will be performing cable trenching, burial works.
The F/V SEAFARER will be operating around the activities as a safety vessel to monitor traffic and facilitate safe movement of fishing vessels, recreational craft, or other transiting vessels around the work sites and project vessels.
Standing by on VHF channel 16
LOCATION(S): Array cable lines 4, 5, 6, 8-1 and 9-1
ISAAC NEWTON
Flag: Luxembourg
Length: 453’
MMSI: 253134000
C-PIONEER
Flag: USA
Length: 260’
MMSI: 368291370
ADHEMAR DE SAINT-VENANT
Flag: Luxembourg
Length: 312’
MMSI: 253351000
F/V SEAFARER
Flag: USA
Length: 76’
MMSI: 367179650
F/V Socatean
Flag: USA
Length: 72’
MMSI: 368085730
VINEYARD WIND
Crista Bank, Fisheries Manager, Cell: 508-525-0421 • Email: cbank@vineyardwind.com
Jeannot Smith, Marine Liaison, Cell: 904-613-0134 • Email: jsmith@vineyardwind.com
Travis Lowery, Fisheries Liaison, Cell: 508-728-4529 • Email: tlowery@vineyardwind.com
VineyardWind.com • info@vineyardwind.com • 508-717-8964
700 Pleasant Street, Suite 510 • New Bedford, MA 02740