TRANSITION PIECE INSTALLATION

OFFSHORE WIND MARINER UPDATE NO. 101

STATUS: Active

Beginning in May, the jack-up vessel SEA CHALLENGER will be installing transition pieces at 17 monopile locations in Lease Area OCS-A 0501.

Standing by on VHF channel 16

 
DATE(S): Beginning in May and continuing through June 2024

LOCATION(S): OCS-A 0501 Lease Area

 

SEA CHALLENGER

Flag: Denmark

Length: 434’

MMSI: 219019002