SUBSEA ROCK INSTALLATION: CPS STABILIZATION (#108)
Offshore wind mariner update NO. 108
STATUS: Active
Beginning on or around August 16, 2024 and continuing through late September, subsea rock installation activities for the Cable Protection System will be conducted by the SIMON STEVIN. This work will involve the placement of rock berms at turbine locations within the lease area OCS-A 0501 wind development area.
Standing by on VHF channel 16
LOCATION(S): Turbine locations within lease area OCS-A 0501 wind development area
VESSELS:
SIMON STEVIN
Flag: LUXEMBOURG
Length: 627’
MMSI #: 253309000
VINEYARD WIND
Crista Bank, Fisheries Manager, Cell: 508-525-0421 • Email: cbank@vineyardwind.com
Jeannot Smith, Marine Liaison, Cell: 904-613-0134 • Email: jsmith@vineyardwind.com
Travis Lowery, Fisheries Liaison, Cell: 508-728-4529 • Email: tlowery@vineyardwind.com
VineyardWind.com • info@vineyardwind.com • 508-717-8964
700 Pleasant Street, Suite 510 • New Bedford, MA 02740