INTER-ARRAY CABLES (IACs) INSTALLATION (#105)
Offshore wind mariner update NO. 105
STATUS: Active
Beginning on or around July 9th and continuing through September 2024, cable laying operations for the inter-array cables will be conducted. The Cable Laying Vessel CONNECTOR will be conducting cable laying operations for the inter-array cables and will remain on-site until mid-August. The C-PIONEER will be acting as a stationary support vessel, supporting cable pulling activities for the inter-array cables. The Trenching Support Vessel SYMPHONY will be performing cable trenching, burial works.
Standing by on VHF channel 16
LOCATION(S): Inter-array cable locations within lease area OCS-A 0501
VESSELS:
C-PIONEER
Flag: USA
Length: 260’
MMSI #: 368291370
SYMPHONY
Flag: LUXEMBOURG
Length: 427’
MMSI #: 253830000
CLV CONNECTOR
Flag: LUXEMBOURG
Length: 515’
MMSI #: 253751000
VINEYARD WIND
Crista Bank, Fisheries Manager, Cell: 508-525-0421 • Email: cbank@vineyardwind.com
Jeannot Smith, Marine Liaison, Cell: 904-613-0134 • Email: jsmith@vineyardwind.com
Travis Lowery, Fisheries Liaison, Cell: 508-728-4529 • Email: tlowery@vineyardwind.com
VineyardWind.com • info@vineyardwind.com • 508-717-8964
700 Pleasant Street, Suite 510 • New Bedford, MA 02740