Posts tagged Barnstable
Centerville. Ma – Hyannis, Ma

Vineyard Wind and its contractors will be testing underground cables throughout the onshore cable route during the week of October 16. This will entail intermittent presence along various locations of the route for a matter of minutes at a time. No road closures will be implemented for this work and one lane alternating traffic will be in place with traffic detailing for public safety. Activity will occur between 7:00am-5:00pm Monday – Thursday, weather permitting with traffic monitoring in place.  

Read More
activeMoreschiBarnstable
Attucks Ln, Hyannis, MA

Vineyard Wind and its contractors will be milling and paving Attucks Ln from Independence Dr to Phinneys Ln Monday – Wednesday this week. One lane alternating traffic will be in place with traffic detailing for public safety. Activity will occur between 7:00am-5:00pm, weather permitting with traffic monitoring in place.  

 

Read More
Phinneys Ln, Hyannis, MA

Vineyard Wind and its contractors will be milling and paving Phinneys Ln from Attucks Ln thru Rte 132 Wednesday - Friday this week. One lane alternating traffic will be in place with traffic detailing for public safety. Activity will occur between 7:00am-5:00pm, weather permitting with traffic monitoring in place.  

Read More
activeMoreschiBarnstable
Craigville Beach Rd, Centerville - Road closed for Splice Vault Installation

Vineyard Wind is working with contractor, Lawrence Lynch who will be mobilizing equipment to this area in preparation to commence splice vault installation for the offshore wind farm. Operations active between 7:00am - 3:30pm daily.

Starting on or after November 18th, Vineyard Wind and its contractors will begin preparation for Horizontal Directional Drilling (HDD) Line 1 at Covell’s Beach Parking Lot. This activity will take place from 7:00am-7:00pm daily and will continue through approximately the week of January 10th 2022.

Read More